MTH601 Assignment no 1 fall 2012 solution uploaded by department of MTH601 VU

Assignment: # 01 (Fall-2012)

Mth601 (Operations Research)

Lecture: 04– 10

 

Question-01 

 

An industrial project has the following data:

 

Activity Immediate Predecessor(s) Time(Days)

A

3

B

4

C

A,B

5

D

B

6

E

D

7

F

C,E

8

G

D

9

 


 

i)                    Draw the network flow diagram.

ii)                  Find the critical path.

iii)                What is the project completion time?

iv)                Compute the total floats (slacks) and free floats for the activities.

Solution:

i)          Network flow diagram:

The longest path is  so our critical path is.

 

iii)                Project completion time:

Expected duration of the project is 25 which is of course the length of the critical path.

      iv )

 

Activity

Early start time

Early Finish time

Late Start time

Late Finish time

Total Float

Free Float

A

0

3

9

12

9

1

B

0

4

0

4

0

0

C

4

9

12

17

8

8

D

4

10

4

10

0

0

E

10

17

10

17

0

0

F

17

25

17

25

0

0

G

10

19

16

25

6

6

     

Total float = (Latest finish time – Early start time) – duration of the activity

Free float = total float – (Latest finish time – Earliest start time for tail event)

 

 

Question-02


 

The following table shows the jobs of a network along with their time estimates. The time estimates are in weeks:

Job 1-2 2-3 2-4 3-5 4-6 4-5 5-7 6-7
Optimistic Time 2 4 4 6 1 3 4 6
Most likely time 5 7 9 10 3 6 5 8
Pessimistic Time 8 10 14 20 5 9 12 10

 

i)                    Find the Critical Path.

ii)                  Compute the probability of completing the project in 36 weeks.

 

Solution:

i)        Critical Path

First calculate the expected time, standard deviation and variance.

 

 

 

The PERT diagram is as follows:

 

 

The possible paths with their expected time of completion are as follows:

Possible Paths             Time

1-2-3-5-7             5+7+11+6   =          29*                  Critical Path

1-2-4-5-7             5+9+6+6     =          26

1-2-4-6-7             5+9+3+8     =          25

Expected project length is 29 weeks.

ii)      Probability of completing project:

Probability that the project completion time T£ 36

Due date=36 weeks (T)

Expected duration=29 weeks (Te)

Variance of Critical Path        =1 + 1 + 5.44 + 1.78

=          9.22

S.D of Critical Path    =

=          3.04

Z          =

=

=          2.30

The area under the normal curve z = 2.30 is 0.4896

P (T£ 36 = P (z£2.30) =0.5+0.4896= 0.9896

_______________________________________

Check Also

MTH601 Assignment no 03 Idea Solution required fall 2013

      Assignment 3 of MTH601 (Fall 2013)                                                            Maximum Marks: 30                                                                                                                                                                                                           Due …

Leave a Reply

Your email address will not be published. Required fields are marked *

*