________ identify which quality standards are relevant to the project and determines how to satisfy them
- Quality planning
- Quality assurance
- Quality control
- Process control
The overall role of Software in a larger system is identified during
- Requirements engineering
- Process engineering
- System engineering
- All of given
The British Standards Institution (1986) has stated the quality as
- The ability of a software product to satisfy its specified requirements
- “An inherent or distinguishing characteristic or a property”
- “Quality is in the eye of the beholder, a matter, of the client’s judgment.”
- All of the given
McCall (MCC77) and his colleagues proposed some software quality factors based on _______ most important aspects of a software product:
- 4
- 3
- 6
- 5
Inefficient project management style is a
- Product-related problems
- Technology-related problems
- Process-related problems
- People-related problems
Upon evaluating current problems and desired information (input and output), the analyst begins to ______
- Synthesize solutions
- Model
- Specification
- All of given
These all are Product Revision Factors except
- Usability
- Maintainability
- Flexibility
- Testability
We can classify the problems that affect software projects into _______ categories
- 3
- 4
- 5
- 6
The check-in and checkout facilities provide_________
- Best control
- Component control
- SCI control
- Synchronization control
The code generation step performs the task
- Translated specification into a machine-readable form
- Translated design into a machine-readable form
- Translated requirements into a machine-readable form
- Translated user data into a machine-readable form
Research-oriented software development is a
- Technology-related problems
- Process-related problems
- People-related problems
- Product-related problems
A meeting is conducted at a _______ and attended by both software engineers and customers.
- Software engineer site
- Neutral site
- Customer site
- Company site
Reviews conducted at each of this phase/s_____
- Analysis
- Design
- Coding
- All of given
All given below are the problems that affect software projects except:
- Product-related problems
- Technology-related problems
- Procedure-related problems
- People-related problems
_______is the technical kernel of software engineering
- Design
- Implementation
- Testing
- Requirement Analysis
Both the software engineer and customer take an active role in software requirements engineering-a set of activities that is often referred to as
- Analysis
- Design
- Specification
- System acceptance
The model serves as the basis for the creation of ______ for the Software.
- Design
- Maintenance
- Testing
- Specifications
Before requirements can be analyzed, modeled, or specified they must be gathered through a/an _______
- Elicitation process
- Interviewing
- Meeting
- None of given
Technology-related problems include _____
- Overestimated savings from reusable components and new tools and methods
- Switching tools in mid-way
- Integrating different software products in cross-platform implementation
- All of given
Insufficient identification is a
- Technology-related problems
- Process-related problems
- People-related problems
- Product-related problems
Throughout evaluation and solution synthesis, the analyst’s primary focus is on ______
- “Not what, not “how”
- “What, also “how”
- “What, not “how”
- None of given
The overall role of Software in a larger system is identified during
- Requirements engineering
- Process engineering
- System engineering
- All of given
In problem evaluation area of effort, once problems have been identified, the ___________determines what information is to be produced by the new system and what data will be provided to the system.
- Analyst
- Designer
- Coder
- Manager
A ‘facilitator’ controls the meeting can be ________
- Customer
- A developer
- An outsider
- All of given
Version control combines ______ to manage different versions of configuration objects that are created during software product development.
- Procedure
- Tools
- Procedure and Tools
- None of given
Many software projects digress from the original scope because of the nature of the software product or technology used, it’s happen in ________
- Product scope changed toward the end of the project life cycle
- Research-oriented software development
- Defined scope
- Fuzzy users
When you build a product or system, it’s important to go through a series of predictable steps – a road map that helps you create a timely, high-quality result, The road map that you follow is called a ________
- Software design
- Software process
- Software schedule
- Framework
Software design is actually a multi step process that focuses on _______ distinct attributes of a program
- 2
- 3
- 4
- 5
When you build a product or system, it’s important to go through a series of predictable steps – a road map that helps you create a timely, high-quality result, The road map that you follow is called a __________
- Software design
- Software Process
- Software schedule
- Framework
The check-in and checkout facilities provide___________
- Best control
- Component control
- SCI control
- Synchronization control
Which of the following might require re-baselining of the cost baseline?
- Corrective action
- Revised cost estimates
- Updates to the cost management plan
- Budget updates
Once the review is complete, the Software Requirements Specification is “signed-off by _________
- Developer
- Customer
- Top level Management
- Both Customer and Developer.
Controlling Versions is activity of ________
- Construction
- Testing
- SCM
- Design
________ identify which quality standards are relevant to the project and determines how to satisfy them
- Quality planning
- Quality assurance
- Quality control
- Process control
The British Standards Institution (1986) has stated the quality as
- The ability of a software product to satisfy its specified requirements
- “An inherent or distinguishing characteristic or a property”
- “Quality is in the eye of the beholder, a matter, of the client’s judgment.”
- All of the given
________ ensures that the standards laid down for a project are followed.
- Quality assurance
- Quality control
- Product evaluation
- Process control
________ ensures that appropriate steps to follow the product development procedures are carried out
- Quality Management
- Design
- Process monitoring
- Quality Control
These all are Product Revision Factors except
- Usability
- Maintainability
- Flexibility
- Testability
To control versions, you can use_____________
- Version Control File
- Version Control Register
- Version Control authority
- All of given
_________is an umbrella activity that ensures conformance to standards and procedures throughout the SDLC of a software product.
- SQA
- Design
- Testing
- All of given
All of the following are benefits of meeting quality requirements
- An increase in stakeholder satisfaction
- Less rework
- Low turnover
- Higher productivity
The Preliminary Users Manual presents the software as a black box: That is, heavy emphasis is placed on
- User input
- User output
- User input and the resultant output
- None of given
Which of the following might require re-baselining of the cost baseline?
- Corrective action
- Revised cost estimates
- Updates to the cost management plan
- Budget updates
Before requirements can be analyzed, modeled, or specified they must be gathered through a/an _______
- Elicitation process
- Interviewing
- Meeting
- None of given
Defined scope is a
- Technology-related problems
- Product-related problems
- Process-related problems
- People-related problems
You can use the Item Traceability Matrix to identify _______ at the end of each phase
- SCIs
- SCM
- Design
- Construction
Most software project manager’s practice a lot of management techniques that are of doubtful authenticity are called
- Project management tools
- Project management myths
- Project management thumb rules
- Project management fundamentals
The Introduction of the software requirements specification states the
- Goals
- Objective
- Design
- Goals and objectives of the software
The code generation step performs the task
- Translated specification into a machine-readable form
- Translated design into a machine-readable form
- Translated requirements into a machine-readable form
- Translated user data into a machine-readable form
———–is the ability to encourage by “push or pull” technical people to produce to their best ability.
- Evaluating
- Motivation
- None of the given
- Monitoring
__________contains an analysis of what went wrong, what went right, and what you could have done better in the software project.
Select correct option:
- Prepare closedown report
- Identify learning
- Identify reusable
- software components
Finally, the specification includes a ________
- Bibliography
- Appendix
- Both Bibliography and Appendix
- None of the above
Product quality depends on its conformance to ______
- Software requirements
- Development standards
- Implicit requirements
- All of given
Given all are major design styles except
- Object
- Procedural
- Structured
- Dtat-Structured Design
The quality of software is said to be high if it meets the
- Standards, defined for the product
- Procedures, defined for the product
- Standards and procedures, defined for the product
- Design defined for product