Question # 1 of 10 ( Start time: 06:21:25 PM)
Total Marks: 1
Which of the following is uncertain in PERT?
Select correct option:
Activity Cost
Activities’ completion times C
Resources associated with each activity
Activities’ precedence relation
BC090401494 : Muhammad Zeeshan
Quiz Start Time: 06:21 PM
Time Left
10
sec(s)
Question # 2 of 10 ( Start time: 06:22:49 PM)
Total Marks: 1
Which of the following event has no immediate predecessor in any network flow diagram?
Select correct option:
Tail Event
Non-Critical Event
C
Head Event
Critical Event
BC090401494 : Muhammad Zeeshan
Quiz Start Time: 06:21 PM
Time Left
49
sec(s)
Question # 3 of 10 ( Start time: 06:24:14 PM)
Total Marks: 1
Which of the following times are not directly related to the activity cost as there is no certainty of time in such activities so their duration cannot be reduced, hence the cost cannot be expressed correctly?
Select correct option:
CPM Times C
PERT Times
BC090401494 : Muhammad Zeeshan
Quiz Start Time: 06:21 PM
Time Left
33
sec(s)
Question # 4 of 10 ( Start time: 06:25:04 PM )
Total Marks: 1
Which of the following distribution gives the probability of completing the assigned project by considering the expected time of any activity as random variable?
Select correct option:
Binomial
Poisson
Beta
C
Normal
BC090401494 : Muhammad Zeeshan
Quiz Start Time: 06:21 PM
Time Left
45
sec(s)
Question # 5 of 10 ( Start time: 06:26:07 PM )
Total Marks: 1
Which of the following relation is true among the probabilistic times in PERT?
Select correct option:
Most Likely < Optimistic < Pessimistic
Optimistic < Most Likely < Pessimistic
C
Most Likely < Pessimistic < Optimistic
Pessimistic < Most Likely < Optimistic
BC090401494 : Muhammad Zeeshan
Quiz Start Time: 06:21 PM
Time Left
34
sec(s)
Question # 6 of 10 ( Start time: 06:27:04 PM )
Total Marks: 1
For a development project, if its Standard Normal variable = 1.38, expected and the scheduled durations of the project are 100 and 110 days respectively, then the Standard Deviation in the project length is —————.
Select correct option:
7.246
-7.246
-52.50
C
52.50
BC090401494 : Muhammad Zeeshan
Quiz Start Time: 06:21 PM
Time Left
68
sec(s)
Question # 7 of 10 ( Start time: 06:28:03 PM)
Total Marks: 1
Which of the following technique to solve the net work flow diagrams, is activity oriented?
Select correct option:
Programme Evaluation and Review Technique C
Critical Path Method
BC090401494 : Muhammad Zeeshan
Quiz Start Time: 06:21 PM
Time Left
69
sec(s)
Question # 8 of 10 ( Start time: 06:28:29 PM )
Total Marks: 1
In a network flow diagram, if an event is the predecessor of three other events then how many dummies are inevitable to include in the network?
Select correct option:
One
Two
Four
Three
C
BC090401494 : Muhammad Zeeshan
Quiz Start Time: 06:21 PM
Time Left
78
sec(s)
Question # 9 of 10 ( Start time: 06:28:55 PM )
Total Marks: 1
For a development project, if its Standard Normal variable = 1.38, expected and the scheduled durations of the project are 100 and 110 days respectively, then Variance in the project length is —————.
Select correct option:
-7.246
-52.50
52.50
C
7.246
BC090401494 : Muhammad Zeeshan
Quiz Start Time: 06:21 PM
Time Left
79
sec(s)
Question # 10 of 10 ( Start time: 06:29:10 PM)
Total Marks: 1
Which of the following technique to solve the network flow diagrams, is event oriented?
Select correct option:
Programme Evaluation and Review Technique
Critical Path Method