MTH601 Quiz 01 Spring 2013 for Mid term papers

Question # 1of 10 ( Start time: 10:17:44 AM) Total Marks: 1

While finding the Critical Path, in the phase of Early Start and Early Finish computations, we start from first event and proceed calculations from left to right up to the ———- event.

Select correct option:
starting

middle

last
arbitrary

Question # 2 of 10 ( Start time: 10:19:03 AM ) Total Marks: 1

In a project, a network diagram shows the ———— relations of the inter related activities along with their corresponding activity times.

Select correct option:
deterministic and probabilistic

precedence or succession
union and intersection

dummy and artificial

Question # 4 of 10 ( Start time: 10:21:58 AM ) Total Marks: 1

In a network flow diagram, if an activity (i,j) starts earlier after two days and finish earlier on fifth day, then which of the following will be its completion time?

Select correct option:
Three days
Five days


Two days

Ten days

Question # 5 of 10 ( Start time: 10:23:24 AM ) Total Marks: 1

While finding the critical path in a network flow diagram, if an activity (i,j) starts and finish late on 3rd and 9th day respectively, then it will be completed in ———–days.

Select correct option:
Three days

Twelve days

Fifteen days

Six days

Question # 6 of 10 ( Start time: 10:24:39 AM) Total Marks: 1

In a network flow diagram, for an activity (i,j) of six days duration, if its Late Finish time is of nine days, then which of the following will be its Late Start time?

Select correct option:
Twelve days
Fifteen days
Three days
Six days

Question # 7of 10 ( Start time: 10:25:42 AM) Total Marks: 1

A/An ———– is the collection of inter related activities to be performed in a particular sequence to completion.

Select correct option:
node

event

project
branch

Question # 8of 10 ( Start time: 10:26:34 AM) Total Marks: 1

In a network flow diagram, for an activity (i,j) of duration of three days, if its earliest start time is of two days then which of the following will be its early finish time?

Select correct option:
Six days

One day


One and half day

Five days

Question # 9 of 10 ( Start time: 10:27:01 AM ) Total Marks: 1

In a network flow diagram, if two jobs ‘a(l,n)’ and ‘b(m,n)’ of ‘7’ and ‘8’ days durations respectively, start earlier simultaneously on 4th day, then the next activity containing ‘n’ as head event can’t start until the entering activity ————– is completed.

Select correct option:
(m,n)
(l,n)

(m,l)

(l,m)

Question # 10 of 10 ( Start time: 10:27:46 AM) Total Marks: 1

About which of the following it is true that, “they only signify with the passage of time, the beginning and ending of some activities under no consumption of resources” ?

Select correct option:
project

nodes
dummy

branch

Check Also

MTH601 Assignment no 03 Idea Solution required fall 2013

      Assignment 3 of MTH601 (Fall 2013)                                                            Maximum Marks: 30                                                                                                                                                                                                           Due …

One comment

  1. please solve it thnks

Leave a Reply

Your email address will not be published. Required fields are marked *

*